angang steel's three new production lines reach design capacity, achieving full-range production capability for new energy silicon steel series
2025-07-09top silicon steel 2025-07-09
on june 30th, ansteel's silicon steel division announced that its three newly constructed production units for the new energy path achieved design capacity within just three months of operation. specifically, the ap2 rolling mill, no. 3 mill, and aa1 unit exceeded design capacities by 304t, 699t, and 2,077t respectively, setting industry records. setting new industry records. with stable operations and controlled quality, this milestone confirms full production capability for ansteel's new energy silicon steel series.
as dedicated lines for nev traction motor silicon steel, these units faced challenges including new personnel, equipment, and processes. stringent technical requirements, thin-gauge rolling complexities, and rigorous quality standards made capacity attainment demanding.
the division adopted the "categorize, detail, implement" principle, carrying out these measures:
decomposed equipment, process, and staffing tasks with timelines and daily tracking
deployed leadership for on-site supervision and real-time issue resolution
formed rolling/annealing task forces with mentorship programs and benchmarking
implemented 24/7 patrols with rapid response and predictive maintenance
optimized edge drop control, trimming temperature, and rolling parameters through r&d
these actions boosted yield and efficiency, with the no. 3 mill breaking shift records three times consecutively in june, achieving industry-leading performance.